Construction General Conditions: What They Are and How to Calculate Them

3 Workers Analyzing Construction Plans

On most construction projects, the general conditions in construction play a pivotal role. The general contractor is responsible for providing professional services that assist all the contractors on site in performing their work. These professional services include supervision, temporary utilities, site security, safety controls, permits, and several other categories of costs. It’s important for general contractors to include these costs in their proposals, as they can add up quickly and are necessary for the project to be completed.

In this article, we are going to look at what general conditions in construction are, how they differ from general requirements and overhead costs, and how to calculate them for your next project.

What are general conditions in construction ?

General conditions can be found in three places on a construction project: the project contract, the specifications, and the project costs. In each of these locations, general conditions mean something slightly different.

In the project contract, the general conditions of the contract for construction are contract terms that define the relationship between the owner, contractor, and possibly the architect. Provisions include the roles and responsibilities of each of the construction contract parties, important dates such as the commencement date and substantial completion, how to handle delays, payment terms, changes to the work, and how claims and disputes will be handled. The most widely used version of general conditions is that provided by the AIA. Most of the contract templates the AIA provides use the A201 General Conditions as the basis for the contract terms.

In a project’s specifications, the construction general conditions checklist or general requirements provide information to contractors about project administration roles, responsibilities, and processes. For example, the requirements include information on project meetings, submittal processing, how change orders will be handled, etc. These detailed terms are project specific and often provide more guidance than the contract general conditions, which may be boilerplate.

As far as project costs go, general conditions costs in construction represent the costs required to provide the infrastructure and resources for the general contractor and trade subcontractors to complete all phases of a construction project. These costs are usually carried out by the general contractor for the benefit of everyone on the project.

Post projects in minutes, drive more business. Find over + 300,000 qualified subcontractors and get to work quicker. Request a demo!

What types of costs are included in general conditions?

The project costs that are included in general conditions are generally made up of four categories: site management, project management, material handling, and trash removal.

Site management costs include providing the infrastructure for the project. This includes providing temporary utilities, such as electricity and water, temporary offices for meetings, portable toilets, erosion control, temporary fencing, lighting, building permits, safety controls, etc. These items are required for everyone on the specfic job to perform their work safely.

Project business management costs include the labor required by the general contractor to oversee and assist trade contractors in completing the work. A general contractor’s team may consist of a project manager, project engineer, superintendent, and foreman. The GC’s supervision is required to ensure that the project meets the construction contract documents, comprised of the drawings and specifications.

Material handling costs include equipment rental and labor to accept delivery of, protect, and stage materials and products for the project. These costs may also include security to protect materials from theft or vandalism.

Finally, construction general conditions examples like trash removal is considered part of the general conditions of a project. Usually, the general contractor is responsible for providing dumpsters and recycling bins for debris generated by the project. In addition, the general contractor may provide labor to clean the site daily to prevent safety hazards and keep the project looking professional.

Overall, general conditions in construction provide a blueprint for project management, outlining the rules and requirements for a successful project. By understanding these conditions thoroughly, leveraging data, and embracing technology, contractors and project owners alike can ensure smooth project execution and, ultimately, successful project delivery.

General Conditions In Construction vs general requirements

As was mentioned above, the general conditions in construction on a project are the costs required by the general contractor to create and maintain a safe and efficient job site. They include project supervision, temporary and permanent utilities, equipment rental, fencing, security, permits, etc.

The conditions of contract in construction or general requirements are provided in the specifications under CSI Division 1 and detail the methods and processes that will be used to complete the project. They define processes for submittals, requests for information (RFIs), change order review, etc.

Are General Conditions Construction Costs overhead?

General conditions construction are not considered overhead. They are costs attached to a specific project that helps the entire project team complete the work required by the contract. Overhead costs are the general costs of doing business that is incurred by all contractors and is not tied to a specific project.

General conditions for construction are costs incurred that lead to project success, while overhead are costs incurred that lead to company success. In addition, a contractor is responsible for paying overhead costs whether a job is in progress or not, while general conditions costs are paid for a specific job.

How to calculate General Conditions Construction Costs

The best way to calculate general conditions construction costs is to look at past cost data. By reviewing similar projects of similar duration, you’ll be able to accurately estimate your costs on the current project. Be sure to add room for price increases, especially in these turbulent economic times.

If you don’t have past project data to look at, you’ll have to price each part of the general conditions separately. General conditions are usually priced for the duration of the project, so knowing how long the project is expected to take is key to determining these costs. For example, let’s say a portable toilet cost $100 a month. If the project is expected to take six months, you can allocate $600 for this service. But if the project actually takes nine months, you’ll either absorb the additional $300 or charge the owner through a change order, depending on the cause of the delay.

Once you’ve determined the anticipated schedule for the project, you can estimate your general conditions for construction costs. List each type of cost you’ll need to provide on the project, calculate an approximate monthly project cost, and multiply it by the expected duration of the project. You may want to add an additional amount to each item for contingency or in case the project takes longer than expected.

General conditions in construction are services, equipment, and materials that general contractors provide to ensure that projects are completed as drawn and specified within the project’s schedule. They include costs related to site management, project management, materials handling, and trash removal. General conditions construction costs are different than general requirements and company overhead costs. The best way to estimate general conditions construction costs is to base them on prior project data. If you don’t have that, you can list each project cost and multiply it by the duration of the project. It’s important to accurately estimate and manage these costs, as they can quickly go over budget and affect project profitability. Visit PlanHub for all your construction general conditions needs.

What Are General Conditions In Construction?

General conditions in construction refer to a set of contractual and project-related terms and requirements that define various aspects of a construction project. These conditions help establish the framework and rules governing the relationship between the project’s stakeholders, including the owner, general contractor, subcontractors, and often the architect or engineer. General conditions encompass a wide range of provisions and responsibilities that contribute to the successful execution of the construction project.

What Does General Conditions Mean In Construction?

In construction, “general conditions” typically refer to a set of contractual and project-related terms and requirements that define various aspects of a construction project. These conditions help establish the framework and rules governing the relationship between the project’s stakeholders, including the owner, general contractor, subcontractors, and often the architect or engineer. General conditions encompass a wide range of provisions and responsibilities that contribute to the successful execution of the construction project.

What is construction cost management?

Construction cost management involves establishing, monitoring, and controlling a project’s budget. The approved project budget or cost baseline is an educated estimate of how much the project will cost to complete. It includes both hard costs, like material and labor, and soft costs, like insurance and permits. Although the budget is set at the beginning of a project, it can be adjusted throughout the project timeline as changes to the work occur.
The budget is established based on contractor estimates for how long the work will take and the cost of the materials, labor, and equipment needed to perform it. The general contractor uses general contractor software and is responsible for estimating any work they will be self-performing, as well as many of the soft costs that go into a project. Trade subcontractors provide the estimated costs for their scope of work.
As work begins and costs start to come in from suppliers and subcontractors, those costs are matched with the appropriate budget line item. The costs incurred to date are subtracted from the original budget for each line item to determine the budget remaining to be spent. The general contractor monitors budget line items and looks for any potential cost overrun.
If the general contractor finds a potential cost overrun, it is his or her job to find out why the project is over budget and either raise the budget for that line item or lower costs associated with it. Monies can be moved from one line item to another without affecting the overall budget amount. Or the overall budget can be increased to accommodate the cost overrun. The general contractor continues to monitor and control the budget throughout the life of the project.

How to improve construction cost management?

1. Thorough, accurate estimates

A good project budget starts with thorough, accurate cost estimation. You can ensure you have an accurate estimate by verifying your takeoffs. Double check quantities and square footage, even from your subcontractors. Get multiple bids for each trade so you can be sure you have the most competitive pricing. PlanHub can help you reach out to new, qualified subcontractors who are looking for work. Finally, compare your budget to the costs of past projects of similar scope. By doing this, you learn from your experience and will quickly notice if a cost estimate is out of line.

2. Communication

Leadership in construction involves constant communication to all parties involved. Lack of communication on a project can quickly lead to additional costs and delays. To avoid this, make sure that everyone is using the same platform for communication. The platform should be accessible from the office, the field, and on the road when traveling. When everyone is using the same tool, it’s easier to work together to solve problems and keep everyone up to date on upcoming issues before they cause a delay or added costs.

3. Monitor progress

To keep costs and schedules under control, you must monitor the progress of the work on a regular basis. Daily reports should detail the quantity of work completed; not just how many workers were on site each day. Comparing work progress to the schedule will allow you to see when progress is slow and needs to be made up. Continually monitoring the progress of the work helps you see delays when they are small and can still be handled proactively.

4. Quality subcontractors

The key to construction quality management is having quality subcontractors who provide excellent workmanship and quality performance on the job. This could mean they are easy to work with, comply quickly to documentation requests, are communicative, and don’t submit frivolous change orders. It can be difficult to break in new subcontractors, so many avoid it. But often, uncooperative subs cost you more in the long run.

5. Clear scope of work

It is important to define a clear scope of work, both at the project level and with subcontractors. When the work is clearly defined there are less disagreements, fewer change orders, and fewer delays caused by arguing about who does what. A clear scope not only defines what work is to be performed. It also spells out what work is to be provided by others.

6. One stop resource for project data

When project data and documents are spread out in different software applications and in different locations, it can be difficult to find the information you need. Storing all project data – including communications, documents, cost data, reports, budgets, and change orders – in one central location cuts down wasted time looking for information and allows project team members to quickly and easily find what they need and get back to work. An all-inclusive construction project management and accounting solution saves teams time and money and makes communication faster and easier.

Be the first to know

PlanHub insights, resources, and news, sent directly to your inbox.

    				
    					<script src='https://planhub.com/wp-includes/js/jquery/jquery.min.js' id='jquery-core-js'></script>
    <script charset="utf-8" type="text/javascript" src="//js.hsforms.net/forms/embed/v2.js"></script>
    <script>
      hbspt.forms.create({
        region: "na1",
        portalId: "7063061",
        formId: "ced7254f-5c61-49b9-9ce0-6f870b79a958"
      });
    </script>
    				
    			

    Get the report!

    From the very beginning, PlanHub has been a place where people can do meaningful work and build strong relationships.

    Come grow with us! We’re building innovative technologies that simplify preconstruction for everyone.

    Estimation is a simple yet powerful digital estimating tool for general contractors, subcontractors, and suppliers that integrates with PlanHub’s existing Takeoff software
    Create quicker, improved takeoffs effortlessly. PlanHub’s Takeoff aids your team in accurate, faster estimates, minimizing errors, and driving business growth.

    Expand your network and connect with general contractors, subcontractors, owners, architects, and suppliers – not to mention thousands of relevant projects at your fingertips.

    Generate relevant leads, faster and with precision. With access to private, hard-to-find projects, you can connect with architects and owners on projects still in the pre-design and design stages.

    PlanHub’s advanced suite of bid management tools allows you to increase productivity, identify relevant projects using data, build bids with Takeoff, and manage bids through the entire process.